(06-20-2024, 01:21 PM)ElwoodBlues1 link Wrote:Built in 1984, connected to grid in 1991...
Construction of the first 330 MW Qinshan reactor, known as the "Glory of China", commenced in 1983, the foundations were poured in 1985, it was connected to the grid in 1991 and commercial operation began in 1994.
The other reactors built at Qinshan have taken four to seven years from foundations poured to commercial operation.
Of course, the Chinese focused all of their energy and resources on one reactor. How are we going to build seven simultaneously?
“Why don’t you knock it off with them negative waves? Why don’t you dig how beautiful it is out here? Why don’t you say something righteous and hopeful for a change?” Oddball